ATNORTH AS

Org.nr: 919900296

atNorth AS is building a significant Norwegian datacenter footprint with 576 MW of grid capacity reserved, while recently consolidating away from the NO1 price zone.

Active Queue

Production

0 MW

Consumption

576 MW

Cases

5

Active Concessions

Production

0 MW

Consumption

0 MW

Cases

0

Overview

atNorth AS is a datacenter-focused energy consumer pursuing large-scale grid connections across Norway, with 576 MW of active consumption capacity reserved across multiple transformer stations. The company has no concession cases, operating purely as a power consumer rather than a producer. Recent weeks have seen a notable strategic retreat from NO1 connections — withdrawing over 216 MW at Hasle and Minne TRA — while retaining a strong 350 MW position at Ringerike (NO1) and 350 MW at Spanne (NO2) in Karmøy.

Active Regions

Rogaland (Karmøy)Viken (Ringerike)Viken (Lillestrøm)

Strategic Focus

atNorth AS is a pure-play datacenter operator focused on securing large-scale grid consumption capacity at multiple Norwegian locations. Their strategy centers on establishing hyperscale or colocation datacenter campuses in areas with available grid capacity. The company appears to be rationalizing its NO1 portfolio — pulling back from Hasle and Minne TRA connections — while doubling down on Ringerike in the NO1 zone and Spanne (Karmøy) in the NO2 zone, likely attracted by competitive power prices and available transformer capacity in those areas.

Recent Activity

In August 2026, atNorth carried out a significant consolidation of its NO1 grid queue positions, withdrawing a total of approximately 216 MW across Hasle TRA (30 MW reserved + 60 MW in queue) and Minne TRA (50 MW reserved + 46 MW in queue). These withdrawals suggest a deliberate strategic pullback from the eastern Oslo-area grid nodes, potentially due to grid capacity constraints, cost considerations, or a refocusing of datacenter site plans. The company retains strong active positions at Ringerike (176 MW) and Spanne/Karmøy (350 MW).

Karmøy
Eidsvoll
Ringerike
Sarpsborg
Lillestrøm
230consumptionSpanne TRAKarmøyFagne ASIn Queuedatacenter
146consumptionRingerike TRARingerikeGlitre Nett ASReserveddatacenter
120consumptionSpanne TRAKarmøyFagne ASReserveddatacenter
50consumptionMinne TRAEidsvollElvia Aswithdrawndatacenter
50consumptionFrogner TRALillestrømElvia AsReserveddatacenter
46consumptionMinne TRAEidsvollElvia Aswithdrawndatacenter
30consumptionHasle TRASarpsborgElvia Aswithdrawndatacenter
30consumptionRingerike TRARingerikeGlitre Nett ASReserveddatacenter