Karmøy
Karmøy is a significant offshore wind and grid hub with major Statnett infrastructure investments and strong data centre interest, though large-scale offshore ambitions have been tempered by project withdrawals.
Active Queue
Production
692 MWConsumption
455 MWCases
9Active Concessions
Production
102 MWConsumption
0 MWCases
18Overview
Karmøy hosts a dense concentration of energy activity centred on offshore wind demonstration projects, grid reinforcement by Statnett and Fagne, and a growing queue of consumption projects including data centres and hydrogen. While the landmark 1,500 MW coordinated Utsira Nord grid connection and a 1,000 MW offshore wind queue reservation were both withdrawn, 691.7 MW of active production capacity and 455 MW of active consumption remain in the grid queue. The municipality is home to key 300/132/66 kV infrastructure at Spanne, Håvik, and the newly confirmed Karmøy transformer station, making it a critical node for future offshore wind landfall.
Recent Activity
In late July 2026, Statnett's new 300 kV Karmøy transformer station received confirmed concession status, a significant milestone for the regional grid. Also in early July 2026, the petroleum consumption reservation at Spanne TRA was reduced from 120 MW to 55 MW and Equinor Energy AS was removed as the named customer, with no replacement identified — suggesting uncertainty around platform electrification plans at this connection point. A separate withdrawn petroleum reservation grew to 85 MW, reflecting further retrenchment in offshore electrification ambitions.
Key Substations
Municipality Stance
Karmøy appears receptive to energy development, hosting multiple offshore wind demonstration concessions, significant grid infrastructure upgrades, and a growing pipeline of industrial and digital economy consumers. No regulatory opposition is evident from the data.
Outlook
Karmøy is well-positioned as a future offshore wind landfall point, anchored by the newly confirmed 300 kV transformer station and existing 132/66 kV regional infrastructure. The 350 MW atNorth data centre pipeline signals strong digital economy demand. The withdrawal of the coordinated 1,500 MW Utsira Nord connection reduces near-term large-scale offshore wind prospects, but the Utsira Nord licensing process continues with one 500 MW project expected to proceed. Hydrogen (Karmsund Hydrogen, 25 MW) and industrial/flexibility projects add breadth to the demand side. Developers should monitor available capacity at Spanne and Håvik TRA as the petroleum electrification picture clarifies.
| — | 85 | consumption | Spanne TRA | Vår Energi As | withdrawn | petroleum |
| — | 55 | consumption | Spanne TRA | Vår Energi As | Reserved | petroleum |
| ATNORTH AS | 230 | consumption | Spanne TRA | Fagne AS | In Queue | datacenter |
| ATNORTH AS | 120 | consumption | Spanne TRA | Fagne AS | Reserved | datacenter |
| CARBONOR AS | 10 | consumption | Spanne TRA | Fagne AS | withdrawn | industrial |
| Diverse Næringsparken | 70 | consumption | Spanne TRA | Fagne AS | withdrawn | other |
| ECOFISK AS | 4.9 | consumption | Spanne TRA | Fagne AS | withdrawn | aquaculture |
| ENDRA AS | 10 | production | Spanne TRA | Fagne AS | Reserved | solar |
| FLEXFUELS AS | 25 | consumption | Spanne TRA | Fagne AS | In Queue | industrial |
| Havvindaktører (kollektiv) | 1,000 | production | Håvik TRA | Energidepartementet | withdrawn | offshore_wind |