Eidsvoll

Eidsvoll hosts one of Norway's most congested grid queues, with over 870 MW of production capacity seeking connection at Minne transformer station.

Active Queue

Production

871 MW

Consumption

215 MW

Cases

33

Active Concessions

Production

0 MW

Consumption

2 MW

Cases

8

Overview

Minne transformer station is the focal point for an exceptionally large pipeline of solar, wind, and data center projects, with 33 active queue positions spanning 871 MW of production and 215 MW of consumption. The queue is dominated by solar developers, with Pyur Energy AS alone holding 10 positions, alongside significant wind and data center interest. Recent weeks have seen notable withdrawals — including two atNorth data center reservations (96 MW combined) and two Hafslund Magnora Sol solar projects (84 MW combined) — suggesting growing congestion pressure and selectivity among developers.

Recent Activity

High churn at Minne TRA in the last 30 days: atNorth withdrew two data center reservations totalling 96 MW (50 MW reserved + 46 MW in queue), and Hafslund Magnora Sol withdrew two solar projects totalling 84 MW. Offsetting these exits, Akershus Energi Vind AS entered the queue with a new 94 MW wind project, maintaining strong overall interest in the node.

Key Substations

Minne transformatorstasjonGjestad transformatorstasjonHovinmoen transformatorstasjonDal transformatorstasjon

Municipality Stance

Eidsvoll appears receptive to energy development, with substantial concession activity for grid upgrades around Gardermoen airport and a very active queue pipeline. The municipality has not signalled opposition to projects in available data.

Outlook

Minne TRA is a high-demand connection point with a deep and diverse project pipeline, but the recent wave of withdrawals (180+ MW in one month) signals meaningful grid capacity constraints. The Elvia-led 132 kV Gjestad–Hovinmoen–Dal upgrade to serve the Gardermoen area is a positive signal for future capacity expansion. Solar dominates the pipeline and will likely see the first projects reach operation, while wind and data center developments face longer lead times. Developers should factor in a competitive queue environment and monitor grid reinforcement progress closely.

Solar Power
539
Wind Power
238
Other
58
Battery Storage (BESS)
35
Hydropower
1.5
Data Centers
Grid Infrastructure
Transport & EV Charging
AKERSHUS ENERGI VIND AS94productionMinne TRAElvia AsIn Queuewind
AKERSHUS ENERGI VIND AS58productionMinne TRAElvia AsIn Queueother
ARCEM SK-DC1 AS75consumptionMinne TRAElvia AsIn Queuedatacenter
ATNORTH AS50consumptionMinne TRAElvia Aswithdrawndatacenter
ATNORTH AS46consumptionMinne TRAElvia Aswithdrawndatacenter
BONUM PROSJEKT 36 AS50consumptionMinne TRAElvia AsIn Queuedatacenter
DIFFER ENERGY AS5productionMinne TRAElvia AsReservedsolar
DIFFER ENERGY AS5productionMinne TRAElvia AsReservedsolar
EIDSIVA HAFSLUND VIND DA144productionMinne TRAElvia AsIn Queuewind
ENDRA AS60productionMinne TRAElvia AsIn Queuesolar