Tinn
Rjukan is emerging as a major energy hub with nearly 1 GW of hydropower in the queue and large-scale data center, hydrogen, and industrial developments underway at a historic industrial site.
Active Queue
Production
860 MWConsumption
1,229 MWCases
8Active Concessions
Production
4 MWConsumption
112 MWCases
12Overview
Tinn municipality, centered on Rjukan, is seeing a surge of energy interest driven by its abundant hydropower resources and the redevelopment of the historic Rjukan industrial park. Statkraft dominates the grid queue with up to 860 MW of hydro production and over 1,000 MW of consumption queued at Rjukan transformatorstasjon, signaling ambitions for large-scale industrial re-electrification. Green Mountain's data center expansion, Norsk Hydrogen's hydrogen plant, and Hima Seafood's aquaculture facility add further diversity to an already dynamic pipeline, supported by significant grid upgrades from LEDE AS and Statnett.
Recent Activity
In August 2026, Green Mountain AS entered the grid connection queue at Rjukan TRA seeking 112 MW for a new data center development, adding to an already active queue. This reflects continued momentum in Tinn's industrial energy corridor.
Key Substations
Municipality Stance
Tinn appears to be openly supportive of energy development, building on Rjukan's deep industrial heritage. The municipality is facilitating a wide range of projects — from data centers and hydrogen to aquaculture and hydropower — with no concession rejections or withdrawals on record.
Outlook
Tinn's outlook is highly promising. The combination of abundant hydropower potential, a rapidly filling grid queue at Rjukan TRA, and Statnett's 420 kV transmission upgrades linking Rjukan to the broader western Norwegian grid positions the municipality as a tier-one location for energy-intensive industries. The redevelopment of the Rjukan industrial park — with hydrogen, data centers, and potentially large-scale hydro — could represent one of the most significant industrial electrification clusters in Telemark. Developers should monitor grid capacity at Rjukan TRA closely as the queue fills.
| GREEN MOUNTAIN AS | 113 | consumption | Rjukan TRA | Lede AS | In Queue | datacenter |
| GREEN MOUNTAIN AS | 33 | consumption | Rjukan TRA | Lede AS | Reserved | datacenter |
| NORSK HYDROGEN AS | 35 | consumption | Rjukan TRA | Lede AS | Reserved | hydrogen |
| STATKRAFT AS | 8 | consumption | Rjukan TRA | Lede AS | Reserved | hydro |
| STATKRAFT ENERGI AS | 900 | consumption | Rjukan TRA | Statkraft Energi As | In Queue | other |
| STATKRAFT ENERGI AS | 720 | production | Rjukan TRA | Statkraft Energi As | In Queue | hydro |
| STATKRAFT ENERGI AS | 140 | production | Rjukan TRA | Statkraft Energi As | In Queue | hydro |
| STATKRAFT ENERGI AS | 140 | consumption | Rjukan TRA | Statkraft Energi As | In Queue | other |