Froland
Froland is emerging as a significant energy hub with major datacenter, battery, and solar investments queuing for grid capacity at Arendal TRA.
Active Queue
Production
61 MWConsumption
598 MWCases
10Active Concessions
Production
5 MWConsumption
0 MWCases
7Overview
Froland hosts a diverse and growing energy pipeline anchored by large-scale consumption projects — including Morrow Batteries' reserved 88 MW battery factory and two datacenter projects totaling 435 MW in the grid queue. The municipality's concession activity is led by grid infrastructure upgrades (notably the 132 kV lines built to serve Morrow) and small hydropower plants, while 61 MW of solar is queuing for production capacity. A withdrawn 171 MW hydrogen project (North Ammonia) signals that not all ambitions have materialized, but the overall trajectory remains strongly positive.
Recent Activity
In August 2026, multiple projects updated their grid connection points from Arendal Industrinett to Arendal TRA, including Morrow Batteries (88 MW, reserved), Bifrost Edge (285 MW, in queue), and Bulk Data Center (150 MW, in queue). Tesla Norway also entered the queue at Arendal TRA with a 2 MW transport reservation. The withdrawn North Ammonia hydrogen project (171 MW) also updated its connection point despite remaining in withdrawn status.
Key Substations
Municipality Stance
Froland appears receptive to large-scale energy investment, having facilitated major grid infrastructure upgrades for Morrow Batteries and attracting significant datacenter and industrial interest. The municipality has not been an obstacle to concession processes.
Outlook
Froland has strong near-term prospects driven by the Morrow Batteries ramp-up and two large datacenter projects seeking grid capacity at Arendal TRA. If grid capacity expands sufficiently — supported by the recently upgraded 132 kV infrastructure — the municipality could absorb well over 500 MW of new consumption. Solar development (61 MW in queue) adds a production dimension. The withdrawal of the 171 MW North Ammonia hydrogen project is a notable setback for green hydrogen ambitions, but the overall pipeline remains robust. Developers should monitor grid capacity availability at Arendal TRA closely, as competition for connection points is intensifying.
| BIFROST EDGE AS | 285 | consumption | Arendal TRA | Glitre Nett AS | In Queue | datacenter |
| PEGA NORDIC AS | 65 | consumption | Arendal TRA | Glitre Nett AS | In Queue | datacenter |
| BULK DATA CENTERS AS | 150 | consumption | Arendal TRA | Glitre Nett AS | In Queue | datacenter |
| ERNST & YOUNG AS | 7 | consumption | Arendal TRA | Glitre Nett AS | In Queue | other |
| HAFSLUND MAGNORA SOL AS | 22 | production | Arendal TRA | Glitre Nett AS | In Queue | solar |
| Energiea As | 19 | production | Arendal TRA | Glitre Nett AS | In Queue | solar |
| HAFSLUND MAGNORA SOL AS | 11 | production | Arendal TRA | Glitre Nett AS | In Queue | solar |
| MORROW BATTERIES ASA | 212 | consumption | Arendal TRA | Glitre Nett AS | withdrawn | industrial |
| MORROW BATTERIES ASA | 89 | consumption | Arendal TRA | Glitre Nett AS | Reserved | industrial |
| NORTH AMMONIA AS | 171 | consumption | Arendal TRA | Glitre Nett AS | withdrawn | hydrogen |