Stjørdal

Stjørdal serves as a key grid hub with the Eidum substation attracting major datacenter and hydrogen investments, though wind development faces significant regulatory challenges.

Active Queue

Production

24 MW

Consumption

189 MW

Cases

3

Active Concessions

Production

0 MW

Consumption

0 MW

Cases

6

Overview

The municipality benefits from strategic grid infrastructure through the Eidum transformatorstasjon, which has attracted a substantial 180 MW datacenter reservation and hydrogen projects. However, the 90 MW Kopperaa wind project remains inactive after rejection due to Sami reindeer herding concerns, highlighting regulatory complexities in the region.

Recent Activity

Strong activity in early 2026 with a new 24 MW hydro project entering the grid queue and several transport-related concessions being processed, including Tesla charging infrastructure and tunnel construction permits.

Key Substations

Eidum transformatorstasjonSutterø transformatorstasjon

Outlook

Positive prospects driven by the strategic Eidum substation location, with significant datacenter and industrial consumption projects in the pipeline, though renewable production development may face regulatory hurdles similar to the rejected wind project.

Hydropower
24
Grid Infrastructure
Transport & EV Charging
Wind Power
Data Centers
Hydrogen & Ammonia
CLEMENS KRAFT AS24productionEidumTensio ASIn Queuehydro
Meråker Hydrogen As9.2consumptionEidumTensio ASReservedhydrogen
VERNE NORWAY AS180consumptionEidumTensio ASIn Queuedatacenter