Valle
Valle is emerging as a strategic datacenter hub with EdgeConneX securing significant grid capacity at the established Brokke power station.
Active Queue
Production
5.4 MWConsumption
365 MWCases
3Active Concessions
Production
0 MWConsumption
0 MWCases
3Overview
The municipality shows strong energy development activity centered around the Brokke power station, where Å Energi operates existing hydro infrastructure. EdgeConneX has reserved 140 MW of datacenter capacity and has another 225 MW in the grid queue, positioning Valle as a significant datacenter destination leveraging reliable hydro power.
Recent Activity
Major datacenter development by EdgeConneX with 365 MW total capacity planned at Brokke, supported by grid infrastructure upgrades including 132 kV cable replacement and underground 420 kV transmission improvements on the Valle-Tokke border.
Key Substations
Outlook
Excellent prospects for energy-intensive industries given the combination of reliable hydro power, strategic grid location, and demonstrated capacity for large-scale datacenter operations. The Brokke location appears to be a key connection point attracting significant investment.
| KREFTER SOLUTIONS AS | 225 | consumption | Brokke | Lede AS | In Queue | datacenter |
| EDGECONNEX MCN NORWAY AS | 140 | consumption | Brokke | Lede AS | Reserved | datacenter |
| Å ENERGI VANNKRAFT AS | 5.4 | production | Brokke | Glitre Nett AS | Reserved | hydro |