Vestby
Vestby is emerging as a major data center hub with substantial grid investments and solar development, anchored by the strategic Tegneby/Langerud grid complex.
Active Queue
Production
143 MWConsumption
943 MWCases
18Active Concessions
Production
300 MWConsumption
35 MWCases
14Overview
The municipality shows exceptional energy development activity with 32 total projects spanning grid modernization, data center expansion, and renewable energy. Statnett's major 420kV transmission upgrades at Langerud position Vestby as a critical grid node, while Microsoft, Green Mountain, and other tech companies have secured nearly 1GW of data center capacity at Tegneby. Solar developers have also established a strong presence with 63MW of projects in the pipeline.
Recent Activity
ELVIA AS received concession approval for Tegneby switching station on May 6, 2026, supporting the ongoing grid infrastructure expansion to accommodate growing data center demand.
Key Substations
Outlook
Vestby is positioned for continued growth as a data center destination, with nearly 1GW of consumption capacity in various stages of development. The substantial grid investments by Statnett and ELVIA create a strong foundation for further industrial development, while emerging solar projects add renewable energy diversity to the local energy landscape.
| BULK DATA CENTERS AS | 80 | consumption | Tegneby | Elvia As | In Queue | datacenter |
| Green Mountain Enebakk As | 75 | consumption | Tegneby | Elvia As | Reserved | datacenter |
| HAFSLUND CELSIO AS | 41 | consumption | Tegneby | Elvia As | Reserved | industrial |
| HAFSLUND KRAFT AS | 80 | production | Tegneby | Elvia As | Reserved | hydro |
| HAFSLUND MAGNORA SOL AS | 19 | production | Tegneby | Elvia As | Reserved | solar |
| HAFSLUND MAGNORA SOL AS | 6.6 | production | Tegneby | Elvia As | Reserved | solar |
| LARKOLLVEIEN 4 AS | 50 | consumption | Tegneby | Elvia As | Reserved | datacenter |
| MICROSOFT DATACENTER NORWAY AS | 119 | consumption | Tegneby | Elvia As | In Queue | datacenter |
| MICROSOFT DATACENTER NORWAY AS | 13 | consumption | Tegneby | Elvia As | Reserved | datacenter |
| NYDALEN ENERGI AS | 15 | consumption | Tegneby | Elvia As | In Queue | industrial |