Narvik
Narvik is emerging as a major data center and industrial hub in Northern Norway, with massive grid capacity reservations driven by hyperscale computing and hydrogen ambitions.
Active Queue
Production
19 MWConsumption
785 MWCases
10Active Concessions
Production
73 MWConsumption
144 MWCases
24Overview
Narvik is seeing exceptional energy demand growth, anchored by large-scale data center developments in Bjerkvik and the Skoglund industrial area, alongside a 100 MW hydrogen plant in the queue. The Kvandal and Skoglund transformer stations are the critical nodes enabling this expansion, with Nordkraft Industrinett and Statnett both investing heavily in 132–420 kV infrastructure upgrades. A withdrawn 250 MW hydrogen/ammonia reservation (Narvik Green Ammonia) signals that not all large ambitions have materialized, but active queue demand exceeds 780 MW in consumption.
Recent Activity
In late June–early July 2026, Aker Nscale (AKER NSCALE DC DA) received a concession for electrical installations connected to their data center in Bjerkvik, Narvik, representing a re-issuance of their construction permit. A second related case was confirmed in the application stage on 3 July 2026 with no new material developments.
Key Substations
Municipality Stance
Narvik appears highly receptive to large-scale energy and industrial development, with active concessions granted for data centers, hydrogen infrastructure, shore power, and significant grid upgrades — suggesting a pro-development local environment.
Outlook
Narvik has strong forward momentum as a data center destination, leveraging access to renewable hydropower and strategic grid infrastructure at Kvandal and Skoglund. The 420 kV Skoglund station upgrade and multiple Nordkraft Industrinett grid investments signal long-term industrial capacity planning. The hydrogen segment carries promise but also risk, as evidenced by Narvik Green Ammonia's 250 MW withdrawal. Developers targeting data center or large industrial loads should prioritize early queue positions at Kvandal TRA, as demand pressure is already intense.
| AKER NSCALE AS | 140 | consumption | Ballangen | Nordkraft Industrinett | In Queue | datacenter |
| Foldvik Kraftverk | 7.8 | production | Kvandal TRA | Noranett AS | Reserved | hydro |
| FRANZEFOSS MINERALS AS | 4.3 | consumption | Skjomen KRA | Noranett AS | In Queue | industrial |
| Narvik Green Ammonia | 250 | consumption | Kvandal TRA | Nordkraft Industrinett | withdrawn | hydrogen |
| NARVIK HYDROGEN AS | 100 | consumption | Sildvik KRA | Narvik Hydrogen AS | In Queue | hydrogen |
| NARVIKFJELLET ALLMENN AS | 8.5 | consumption | Narvik TRA | Noranett AS | Reserved | other |
| PLUG NORD AS | 12 | consumption | Narvik TRA | Noranett AS | Reserved | transport |
| STATKRAFT ENERGI AS | 11 | production | Skjomen KRA | Statkraft Energi As | Reserved | hydro |
| Aaktik Digital As | 230 | consumption | Kvandal TRA | Nordkraft Industrinett | Reserved | datacenter |
| Aaktik Digital | 200 | consumption | Kvandal TRA | Nordkraft Industrinett | In Queue | datacenter |