Narvik
Narvik is emerging as a major digital and industrial hub with significant datacenter development and grid infrastructure expansion to support energy-intensive industries.
Active Queue
Production
19 MWConsumption
786 MWCases
10Active Concessions
Production
73 MWConsumption
144 MWCases
21Overview
The municipality shows exceptional activity with 31 total energy projects, including substantial datacenter investments totaling nearly 800 MW and major grid upgrades. Strong industrial focus with hydrogen production facilities, cruise ship electrification, and aquaculture development alongside existing wind and hydro assets.
Recent Activity
Significant progress in April 2026 with Skoglund transformer station receiving concession, AN SITE 4 AS delaying datacenter connection, Narvik Hydrogen increasing capacity to 100 MW, and cruise shore power moving to public hearing phase
Key Substations
Municipality Stance
Highly supportive of energy development and industrial electrification, actively facilitating major datacenter and hydrogen investments
Outlook
Excellent prospects as a major digital and green industrial hub, with substantial grid capacity being developed to support energy-intensive industries including datacenters, hydrogen production, and transport electrification
| AKER NSCALE AS | 140 | consumption | Ballangen | Nordkraft Industrinett | In Queue | datacenter |
| AN SITE 4 AS | 5 | consumption | Kvandal | Noranett AS | Reserved | datacenter |
| Foldvik Kraftverk | 7.8 | production | Kvandal | Noranett AS | Reserved | hydro |
| Narvik Green Ammonia | 250 | consumption | Kvandal | Nordkraft Industrinett | withdrawn | hydrogen |
| NARVIK HYDROGEN AS | 100 | consumption | Sildvik | Narvik Hydrogen AS | In Queue | hydrogen |
| NARVIKFJELLET ALLMENN AS | 8.5 | consumption | Narvik | Noranett AS | Reserved | other |
| PLUG NORD AS | 12 | consumption | Narvik | Noranett AS | Reserved | transport |
| STATKRAFT ENERGI AS | 11 | production | Skjomen | Statkraft Energi As | Reserved | hydro |
| Aaktik Digital As | 230 | consumption | Kvandal | Nordkraft Industrinett | Reserved | datacenter |
| Aaktik Digital | 200 | consumption | Kvandal | Nordkraft Industrinett | In Queue | datacenter |