Nordreisa is experiencing modest energy infrastructure development with aquaculture demand driving grid modernization and one major wind project recently approved.
Active Queue
Production
0 MWConsumption
11 MWCases
2Active Concessions
Production
0 MWConsumption
0 MWCases
5Overview
The municipality has 5 active concession cases primarily focused on grid infrastructure improvements, including the expansion of Vinnelys transformer station and the 420 kV Balsfjord-Skaidi transmission line. Aquaculture companies Mowi and Lerøy have secured grid capacity totaling 11 MW, indicating growing industrial demand in the region.
Recent Activity
Mowi's grid capacity reservation at Vinnelys was reduced from 9.8 MW to 5 MW in early April 2024, suggesting project refinement or scaling adjustments.
Key Substations
Outlook
The municipality shows steady development potential with significant grid infrastructure investments creating capacity for industrial growth. The successful approval of the Maurneset wind project after previous rejection indicates improving conditions for renewable energy development, while aquaculture demand provides a stable foundation for grid expansion.
| LERØY AS | 5.6 | consumption | Vinnelys | Vissi AS | Reserved | aquaculture |
| MOWI ASA | 5 | consumption | Vinnelys | Vissi AS | In Queue | aquaculture |