Luster

Luster is a high-activity energy municipality dominated by Hydro's large-scale pumped storage development and significant industrial and datacenter grid queue demand.

Active Queue

Production

207 MW

Consumption

430 MW

Cases

17

Active Concessions

Production

208 MW

Consumption

0 MW

Cases

19

Overview

Luster hosts a concentrated cluster of energy activity centered on Hydro Energi's major pumped storage investments at Illvatn and Øyane, supported by extensive new 132 kV and 420 kV grid infrastructure at Jamnene/Fortun. The Statnett grid queue reflects substantial demand from Hydro Aluminium's industrial expansion (162 MW consumption) and two large datacenter projects (220 MW combined) at Leirdøla, alongside multiple smaller hydropower capacity additions. With no withdrawn queue items and only one dismissed concession, the municipality shows a healthy and stable development environment.

Recent Activity

No concession changes or queue withdrawals are indicated in the last 30 days. Activity is ongoing across Hydro Energi's pumped storage and grid upgrade projects, and the two large datacenter queue reservations at Leirdøla (Gaupne Utvikling and Kitebrook) represent significant emerging demand.

Key Substations

Jamnene transformatorstasjon (420/300 kV, Fortun)Jamnene koblingsstasjonFortun transformatorstasjon (132 kV)Leirdøla (LEX) transformatorstasjonSveinsøystølen (132 kV, Illvatn)

Municipality Stance

Luster appears highly receptive to energy development, with a strong track record of granted concessions and no sign of municipal opposition. The municipality is deeply integrated into Hydro's industrial and hydropower operations, and is emerging as a datacenter destination at Gaupne/Leirdøla.

Outlook

Luster's outlook is strong. The Jamnene 420 kV transformer station upgrade significantly expands the area's grid backbone, facilitating both Hydro Aluminium's industrial load growth and new datacenter entrants. The Fortun KRA/TRA connection point is active with multiple hydropower queue reservations, suggesting continued small and medium hydro development. The Leirdøla connection point is emerging as a dedicated hub for large-scale power consumption. Developers should monitor grid capacity at both connection points as industrial and datacenter demand grows.

Hydropower
159
Other
48
Grid Infrastructure
Industrial
Data Centers
5.6productionLeirdøla (LEX) TRASygnir ASReservedhydro
FORTE VANNKRAFT AS24productionFortun KRA/TRALinja ASReservedhydro
GAUPNE UTVIKLING AS120consumptionLeirdøla (LEX) TRASygnir ASReserveddatacenter
HYDRO ALUMINIUM AS56consumptionFortun KRA/TRALinja ASIn Queueindustrial
HYDRO ALUMINIUM AS40consumptionFortun KRA/TRALinja ASIn Queueindustrial
HYDRO ALUMINIUM AS40consumptionFortun KRA/TRALinja ASIn Queueindustrial
HYDRO ALUMINIUM AS26consumptionFortun KRA/TRALinja ASReservedindustrial
HYDRO ENERGI AS51productionFortun KRA/TRALinja ASReservedhydro
HYDRO ENERGI AS48productionFortun KRA/TRALinja ASReservedother
HYDRO ENERGI AS48consumptionFortun KRA/TRALinja ASReservedother
110 of 17