Åseral

Åseral shows strong hydropower development activity with significant expansion projects by Å Energi, despite past wind power setbacks.

Active Queue

Production

19 MW

Consumption

0 MW

Cases

1

Active Concessions

Production

147 MW

Consumption

0 MW

Cases

8

Overview

The municipality is experiencing robust energy development primarily driven by Å Energi's major hydropower expansion projects totaling 143 MW. While the large Honna wind project faced regulatory rejection due to environmental concerns, substantial hydropower infrastructure development continues with multiple grid connections and upgrades underway.

Recent Activity

No specific activity reported in the last 30 days, but multiple approved projects are in various stages of development with active grid connections being established.

Key Substations

Honna transformatorstasjonSmeland kraftstasjonGlitre Nett nettstasjon

Municipality Stance

Generally supportive of hydropower development but environmental concerns have impacted wind projects, particularly regarding wild reindeer migration corridors.

Outlook

Strong prospects for hydropower expansion with Å Energi leading major infrastructure investments. Grid capacity improvements through Honna substation position the municipality well for future renewable energy connections, though wind development may face continued environmental scrutiny.

Hydropower
19
Grid Infrastructure
Wind Power
Other
Å ENERGI VANNKRAFT AS19productionHonnaGlitre Nett ASReservedhydro