Hamar

Hamar is experiencing massive energy development centered around Vang substation, with over 1,800 MW of renewable projects and data centers in the pipeline.

Active Queue

Production

1,456 MW

Consumption

237 MW

Cases

39

Active Concessions

Production

140 MW

Consumption

180 MW

Cases

8

Overview

The municipality has become a major energy hub with significant solar, wind, and data center development all connecting to the strategically important Vang transformer station. The approved 180 MW Green Mountain data center and 140 MW Vang solar plant demonstrate strong municipal support, while extensive grid infrastructure upgrades by Statnett and Elvia are enabling this transformation.

Recent Activity

Major approvals include the 180 MW Green Mountain data center and associated grid infrastructure, plus the 140 MW Vang solar plant application, with 39 additional projects totaling over 1,800 MW in the grid queue

Key Substations

Vang transformatorstasjonBørstad transformatorstasjonBrumunddal transformatorstasjonHamar omformerstasjon

Municipality Stance

Highly supportive of energy development, having approved major data center and solar projects while facilitating extensive grid infrastructure upgrades

Outlook

Exceptional growth potential with Vang substation becoming a regional energy hub, though grid capacity constraints may require careful sequencing of the numerous queued projects

End CustomerMWProd/ConsStationStatusType
Aneo AS17productionVangReservedsolar
Aneo AS10productionVangIn Queuesolar
BaneNor SF24consumptionVangReservedtransport
Carbon Centric AS14consumptionVangIn Queueindustrial
Differ Energy AS15productionVangIn Queuesolar
Differ Energy AS14productionVangIn Queuesolar
Differ Energy AS6productionVangIn Queuesolar
Differ Energy AS5productionVangIn Queuesolar
Eidsiva Bredbånd AS10consumptionVangReserveddatacenter
Eidsiva Hafslund Vind DA43productionVangIn Queuewind
110 of 39