Sandnes

Sandnes is an actively developing energy hub in Rogaland, with significant grid upgrades underway and growing demand from datacenters, transport electrification, and battery storage.

Active Queue

Production

35 MW

Consumption

83 MW

Cases

8

Active Concessions

Production

30 MW

Consumption

0 MW

Cases

15

Overview

Sandnes sits at the heart of South Rogaland's energy infrastructure, anchored by major Statnett and Lnett transmission upgrades including the planned 420 kV Fagrafjell–Bærheim line and the new Humleberget transformatorstasjon. The municipality hosts operational wind capacity at Vardafjellet and a queue of consumption projects at Bærheim TRA spanning datacenters, EV charging, and public transport electrification. Recent queue activity from Lyse Kraft DA at Lyse TRA signals emerging interest in battery storage, adding a new production-and-consumption dynamic to the local grid picture.

Recent Activity

In late June 2026, Lyse Kraft DA entered the queue at Lyse TRA for both 35 MW of production and 35 MW of consumption, likely representing a battery storage project. In July 2026, Uno-X Mobility Norge AS was granted a concession for a network station at Vågsgata to support EV fast-charging infrastructure, reflecting continued growth in transport electrification.

Key Substations

Bærheim transformatorstasjonHumleberget transformatorstasjonSeldal transformatorstasjonFagrafjell transformatorstasjonVagle transformatorstasjonLyse transformatorstasjonHelmikstøl transformatorstasjon

Municipality Stance

No explicit municipal policy stance is evident from the data, but the volume of active concessions and reserved queue positions — spanning grid upgrades, wind, datacenters, and transport — suggests a permissive and infrastructure-forward environment. The 90 MW Sandnes vindkraftverk having previously been stalled on grid capacity rather than local opposition further supports this reading.

Outlook

Sandnes has strong near-term prospects driven by transmission reinforcement (420 kV Fagrafjell–Bærheim upgrade and new Humleberget station), which should unlock additional grid capacity for the Nord-Jæren region. Bærheim TRA is emerging as a key connection point for consumption projects, with datacenters and electrified transport already reserving capacity. The pending Sandnes vindkraftverk (90 MW, now under permit revision) could become a major local production asset if grid bottlenecks are resolved through the ongoing transmission investments. Battery storage interest at Lyse TRA is an early but notable signal of flexibility market activity.

Battery Storage (BESS)
35
Grid Infrastructure
Transport & EV Charging
Data Centers
Wind Power
Other
Hydropower
ASP DATA CENTER AS8consumptionBærheim TRALnett ASIn Queuedatacenter
ASP EIENDOM AS8consumptionBærheim TRALnett ASReserveddatacenter
ASP EIENDOM AS3consumptionBærheim TRALnett ASReserveddatacenter
AVINOR AS9.6consumptionBærheim TRALnett ASIn Queuetransport
KOLUMBUS AS18consumptionBærheim TRALnett ASReservedtransport
LYSE KRAFT DA35consumptionLyse TRALnett ASIn Queuebattery
LYSE KRAFT DA35productionLyse TRALnett ASIn Queuebattery
LYSE NEO AS1.1consumptionBærheim TRALnett ASIn Queueother