Sandnes
Sandnes is an actively developing energy hub in Rogaland, with significant grid upgrades underway and growing demand from datacenters, transport electrification, and battery storage.
Active Queue
Production
35 MWConsumption
83 MWCases
8Active Concessions
Production
30 MWConsumption
0 MWCases
15Overview
Sandnes sits at the heart of South Rogaland's energy infrastructure, anchored by major Statnett and Lnett transmission upgrades including the planned 420 kV Fagrafjell–Bærheim line and the new Humleberget transformatorstasjon. The municipality hosts operational wind capacity at Vardafjellet and a queue of consumption projects at Bærheim TRA spanning datacenters, EV charging, and public transport electrification. Recent queue activity from Lyse Kraft DA at Lyse TRA signals emerging interest in battery storage, adding a new production-and-consumption dynamic to the local grid picture.
Recent Activity
In late June 2026, Lyse Kraft DA entered the queue at Lyse TRA for both 35 MW of production and 35 MW of consumption, likely representing a battery storage project. In July 2026, Uno-X Mobility Norge AS was granted a concession for a network station at Vågsgata to support EV fast-charging infrastructure, reflecting continued growth in transport electrification.
Key Substations
Municipality Stance
No explicit municipal policy stance is evident from the data, but the volume of active concessions and reserved queue positions — spanning grid upgrades, wind, datacenters, and transport — suggests a permissive and infrastructure-forward environment. The 90 MW Sandnes vindkraftverk having previously been stalled on grid capacity rather than local opposition further supports this reading.
Outlook
Sandnes has strong near-term prospects driven by transmission reinforcement (420 kV Fagrafjell–Bærheim upgrade and new Humleberget station), which should unlock additional grid capacity for the Nord-Jæren region. Bærheim TRA is emerging as a key connection point for consumption projects, with datacenters and electrified transport already reserving capacity. The pending Sandnes vindkraftverk (90 MW, now under permit revision) could become a major local production asset if grid bottlenecks are resolved through the ongoing transmission investments. Battery storage interest at Lyse TRA is an early but notable signal of flexibility market activity.
| ASP DATA CENTER AS | 8 | consumption | Bærheim TRA | Lnett AS | In Queue | datacenter |
| ASP EIENDOM AS | 8 | consumption | Bærheim TRA | Lnett AS | Reserved | datacenter |
| ASP EIENDOM AS | 3 | consumption | Bærheim TRA | Lnett AS | Reserved | datacenter |
| AVINOR AS | 9.6 | consumption | Bærheim TRA | Lnett AS | In Queue | transport |
| KOLUMBUS AS | 18 | consumption | Bærheim TRA | Lnett AS | Reserved | transport |
| LYSE KRAFT DA | 35 | consumption | Lyse TRA | Lnett AS | In Queue | battery |
| LYSE KRAFT DA | 35 | production | Lyse TRA | Lnett AS | In Queue | battery |
| LYSE NEO AS | 1.1 | consumption | Bærheim TRA | Lnett AS | In Queue | other |