Oslo is a high-activity consumption hub with strong demand from data centers, transport electrification, carbon capture, and major grid upgrades anchoring the city's energy transition.
Active Queue
Production
5 MWConsumption
161 MWCases
16Active Concessions
Production
0 MWConsumption
131 MWCases
66Overview
Oslo shows significant and diverse energy development activity, dominated by consumption-side projects totalling over 292 MW across concessions and the Statnett queue. Key drivers include data center expansion at Ulven and Furuset, the Fornebubanen metro extension, Hafslund Celsio's carbon capture facility at Klemetsrud, and large-scale hospital and municipal water infrastructure upgrades. The transmission backbone is being reinforced through Statnett's 420 kV Sogn–Ulven cable and transformer upgrades at Smestad and Sogn, signalling sustained grid investment to meet growing urban demand.
Recent Activity
The past 30 days have seen notable queue activity: Elvia AS submitted twin 5 MW production and consumption connection requests at Ulven TRA (July 2026), indicating potential local flexibility or storage planning. Blix Data Center AS entered the queue for a 10 MW data center at Furuset (June 2026), adding to the growing cluster of data center demand at that substation. Oslo Kommune Vann- og avløpsetaten's 16 MW reservation at Smestad TRA was confirmed (June 2026), reflecting the municipality's expanding power needs for water infrastructure.
Key Substations
Municipality Stance
Oslo actively supports energy infrastructure development, with the municipality itself appearing as a project initiator (Fornebubanen, Vann- og avløpsetaten). The city is enabling electrification of transport, carbon capture, and digital infrastructure, reflecting a pro-development and climate-oriented energy policy.
Outlook
Oslo's energy outlook is strongly demand-driven, with data centers, transport electrification, and industrial decarbonisation (carbon capture) as the primary growth vectors. The Ulven and Furuset substations are emerging as critical connection points for new load, and ongoing Statnett transmission upgrades (420 kV Sogn–Ulven, Smestad reactive compensation) suggest grid capacity is being proactively expanded. Production opportunities are limited given the urban context, though the Elvia queue entry hints at potential battery or flexibility assets. Developers targeting consumption connections should monitor substation capacity at Ulven and Furuset closely, as demand is intensifying.
| BLIX DATA CENTER AS | 10 | consumption | Furuset TRA | Elvia As | In Queue | datacenter |
| BULK DATA CENTERS OS-IX AS | 19 | consumption | Furuset TRA | Elvia As | In Queue | datacenter |
| ELVIA AS | 5 | consumption | Ulven TRA | Elvia As | In Queue | battery |
| ELVIA AS | 5 | production | Ulven TRA | Elvia As | In Queue | battery |
| HAFSLUND CELSIO AS | 7 | consumption | Ulven TRA | Elvia As | Reserved | other |
| HAFSLUND CELSIO AS | 6 | consumption | Furuset TRA | Elvia As | In Queue | other |
| NYDALEN ENERGI AS | 15 | consumption | Sogn TRA | Elvia As | In Queue | other |
| Nye Aker Sykehus | 7.8 | consumption | Furuset TRA | Elvia As | Reserved | other |
| Nye Rikshopistalet Sykehus | 9 | consumption | Sogn TRA | Elvia As | Reserved | other |
| OSLO HAVN KF | 14 | consumption | Smestad TRA | Elvia As | Reserved | transport |