Oslo

Oslo is a high-activity consumption hub with strong demand from data centers, transport electrification, carbon capture, and major grid upgrades anchoring the city's energy transition.

Active Queue

Production

5 MW

Consumption

161 MW

Cases

16

Active Concessions

Production

0 MW

Consumption

131 MW

Cases

66

Overview

Oslo shows significant and diverse energy development activity, dominated by consumption-side projects totalling over 292 MW across concessions and the Statnett queue. Key drivers include data center expansion at Ulven and Furuset, the Fornebubanen metro extension, Hafslund Celsio's carbon capture facility at Klemetsrud, and large-scale hospital and municipal water infrastructure upgrades. The transmission backbone is being reinforced through Statnett's 420 kV Sogn–Ulven cable and transformer upgrades at Smestad and Sogn, signalling sustained grid investment to meet growing urban demand.

Recent Activity

The past 30 days have seen notable queue activity: Elvia AS submitted twin 5 MW production and consumption connection requests at Ulven TRA (July 2026), indicating potential local flexibility or storage planning. Blix Data Center AS entered the queue for a 10 MW data center at Furuset (June 2026), adding to the growing cluster of data center demand at that substation. Oslo Kommune Vann- og avløpsetaten's 16 MW reservation at Smestad TRA was confirmed (June 2026), reflecting the municipality's expanding power needs for water infrastructure.

Key Substations

Ulven transformatorstasjonFuruset transformatorstasjonSmestad transformatorstasjonSogn transformatorstasjonLiåsen transformatorstasjonKlemetsrud 2 transformatorstasjonSolli transformatorstasjon

Municipality Stance

Oslo actively supports energy infrastructure development, with the municipality itself appearing as a project initiator (Fornebubanen, Vann- og avløpsetaten). The city is enabling electrification of transport, carbon capture, and digital infrastructure, reflecting a pro-development and climate-oriented energy policy.

Outlook

Oslo's energy outlook is strongly demand-driven, with data centers, transport electrification, and industrial decarbonisation (carbon capture) as the primary growth vectors. The Ulven and Furuset substations are emerging as critical connection points for new load, and ongoing Statnett transmission upgrades (420 kV Sogn–Ulven, Smestad reactive compensation) suggest grid capacity is being proactively expanded. Production opportunities are limited given the urban context, though the Elvia queue entry hints at potential battery or flexibility assets. Developers targeting consumption connections should monitor substation capacity at Ulven and Furuset closely, as demand is intensifying.

Battery Storage (BESS)
5
Grid Infrastructure
Transport & EV Charging
Other
Data Centers
Industrial
BLIX DATA CENTER AS10consumptionFuruset TRAElvia AsIn Queuedatacenter
BULK DATA CENTERS OS-IX AS19consumptionFuruset TRAElvia AsIn Queuedatacenter
ELVIA AS5consumptionUlven TRAElvia AsIn Queuebattery
ELVIA AS5productionUlven TRAElvia AsIn Queuebattery
HAFSLUND CELSIO AS7consumptionUlven TRAElvia AsReservedother
HAFSLUND CELSIO AS6consumptionFuruset TRAElvia AsIn Queueother
NYDALEN ENERGI AS15consumptionSogn TRAElvia AsIn Queueother
Nye Aker Sykehus7.8consumptionFuruset TRAElvia AsReservedother
Nye Rikshopistalet Sykehus9consumptionSogn TRAElvia AsReservedother
OSLO HAVN KF14consumptionSmestad TRAElvia AsReservedtransport
110 of 16