Oslo

Oslo is a high-demand consumption hub with no local production, driven by data centers, transport electrification, carbon capture, and major grid upgrades.

Active Queue

Production

0 MW

Consumption

156 MW

Cases

14

Active Concessions

Production

0 MW

Consumption

131 MW

Cases

66

Overview

Oslo's energy landscape is dominated by consumption growth across data centers, EV charging, public transport electrification, and large-scale industrial projects such as the Klemetsrud carbon capture facility. The city has 66 active concession cases and 14 active grid queue reservations totalling over 287 MW of combined attributed consumption. Statnett and Elvia are actively reinforcing the transmission grid—including 420 kV upgrades at Sogn and new transformer capacity at Ulven and Liåsen—to meet rising urban demand.

Recent Activity

In late August 2026 Elvia AS withdrew two small (~5 MW) production and consumption queue entries at Ulven TRA, suggesting a minor rebalancing of grid reservation strategy rather than a broader retreat. ST1 Norge AS received a concession for the Åsland project on 4 August 2026. Activity in July–August 2026 otherwise centres on ongoing grid reinforcement and the continued processing of data centre and transport concessions.

Key Substations

Ulven transformatorstasjonSogn transformatorstasjonSmestad transformatorstasjonFuruset transformatorstasjonLiåsen transformatorstasjonKlemetsrud 2 transformatorstasjonSolli transformatorstasjon

Municipality Stance

Oslo actively facilitates energy infrastructure development, particularly for decarbonisation, public transport electrification, and port shore power. The municipality itself is a queue participant (Fornebubanen, Vann- og avløpsetaten), signalling institutional commitment to grid-connected projects. No opposition or restrictive signals are evident.

Outlook

Oslo's consumption demand will continue rising as the Fornebubanen metro extension is completed, Klemetsrud carbon capture scales up, and data centre interest around the Ulven and Furuset substations intensifies. Statnett's 420 kV Sogn–Ulven cable and the new Liåsen transformer station are critical enablers for future capacity. Developers should monitor queue positions at Ulven and Furuset closely, as these nodes are attracting multiple competing large consumers. No production projects are present or planned, so Oslo will remain a pure consumption market reliant on imported power.

Grid Infrastructure
Transport & EV Charging
Other
Data Centers
Industrial
BLIX DATA CENTER AS10consumptionFuruset TRAElvia AsIn Queuedatacenter
BULK DATA CENTERS OS-IX AS19consumptionFuruset TRAElvia AsIn Queuedatacenter
HAFSLUND CELSIO AS7consumptionUlven TRAElvia AsReservedother
HAFSLUND CELSIO AS6consumptionFuruset TRAElvia AsIn Queueother
NYDALEN ENERGI AS15consumptionSogn TRAElvia AsIn Queueother
Nye Aker Sykehus7.8consumptionFuruset TRAElvia AsReservedother
Nye Rikshopistalet Sykehus9consumptionSogn TRAElvia AsReservedother
OSLO HAVN KF14consumptionSmestad TRAElvia AsReservedtransport
OSLO KOMMUNE FORNEBUBANEN13consumptionSogn TRAElvia AsReservedtransport
OSLO KOMMUNE FORNEBUBANEN6.2consumptionSmestad TRAElvia AsReservedtransport