Ntnu Tyholt Marin Center
Org.nr: 000000085
NTNU Tyholt Marin Center withdrew its 7 MW industrial consumption project from grid queue at Strinda in June 2024
Active Queue
Production
0 MWConsumption
0 MWCases
0Active Concessions
Production
0 MWConsumption
0 MWCases
0Overview
This NTNU marine research center had reserved 7 MW of industrial power consumption capacity at Strinda but recently withdrew the project from the grid connection process. The withdrawal suggests the planned industrial facility or expansion has been cancelled or postponed.
Strategic Focus
Marine research facility power consumption for NTNU operations, though recent project withdrawal indicates revised plans
Recent Activity
Withdrew 7 MW industrial power consumption project from grid queue at Strinda station in June 2024, removing all active energy development activity