Ntnu Tyholt Marin Center

Org.nr: 000000085

NTNU Tyholt Marin Center withdrew its 7 MW industrial consumption project from grid queue at Strinda in June 2024

Active Queue

Production

0 MW

Consumption

0 MW

Cases

0

Active Concessions

Production

0 MW

Consumption

0 MW

Cases

0

Overview

This NTNU marine research center had reserved 7 MW of industrial power consumption capacity at Strinda but recently withdrew the project from the grid connection process. The withdrawal suggests the planned industrial facility or expansion has been cancelled or postponed.

Strategic Focus

Marine research facility power consumption for NTNU operations, though recent project withdrawal indicates revised plans

Recent Activity

Withdrew 7 MW industrial power consumption project from grid queue at Strinda station in June 2024, removing all active energy development activity